Once one of the top three largest shopping malls in the world, Century III Mall in West Mifflin, PA sat vacant and deteriorating for years after closing in 2019.
After years of planning, legal hurdles, and environmental remediation, Neiswonger Construction was awarded the contract to complete the full demolition and site clearing of the property.
Demolition began in 2024 with the removal of parking structures and initial site work. Today, only a small portion of the structure remains, as crews focus on removing the final sections, processing materials on-site, and preparing the property for its next phase of redevelopment.
Please DO NOT enter the site while we are working – if you would like to see what is going on, many of the local Pittsburgh news stations have covered the progress and will share updates from time to time:
WTAE (Pittsburgh): “2 arrested as demolition begins on Century III Mall” (04/01/2024)
WTAE (Pittsburgh): “Demolition could start at Century III Mall” (03/26/2024)
WTAE (Pittsburgh): “Century III Mall Demolition Date Set” (03/28/2024)
KDKA (Pittsburgh): “First phase of demolition set to begin at Century III Mall” (03/26/2024)
Drone Flythrough – December 2024.
Check out this 3-minute video flythrough to see the progress we are making on the demolition of the former Century III Mall.
Thank you to Andrew Rush for providing Drone services.

December 2024 Update
Check out this overview to see the progress we are making on the demolition of the former Century III Mall.
Thank you to Andrew Rush for providing Drone services.

June 2025 Update
Check out this overview to see the progress we are making on the demolition of the former Century III Mall.
Thank you to Andrew Rush for providing Drone services.
Andrew has also put together a photo gallery featuring some updates from June 2025.
You can access those by clicking the yellow button below.